Godrej Brooklyn Avenue Construction Status
Godrej Brooklyn Avenue construction status is in the New Launch / Bookings Open stage as of June 2026. Telangana RERA (TS-RERA) registration is approved — RERA No. P02200010981. The official project launch is scheduled for 25 May 2026. On-site work starts in the weeks that follow. Possession is targeted for June 2031. This page covers the full milestone calendar, the current site status and what to expect at each build stage.
Project Status Snapshot — As of 2026
| Status Item | Detail |
| Current stage | New Launch / Bookings Open — EOI window open |
| Telangana RERA | Approved — RERA No. P02200010981 |
| Official launch date | 25 May 2026 |
| Site mobilisation | Q3 2026 (post-launch) |
| Excavation + piling | Q4 2026 – Q1 2027 |
| Foundation completion | Q2 – Q3 2027 |
| Superstructure rise | Q4 2027 – 2029 |
| Finishing works | 2030 – Q3 2031 |
| Handover / possession | June 2031 |
Full Milestone Calendar
New Launch (Current)
- Telangana RERA (TS-RERA) registration is approved — RERA No. P02200010981; bookings open
- EOI window open — refundable ₹5–6 Lakh reservation locks in the ₹12,500/sq.ft. pre-launch rate
- Kukatpally Experience Centre operational with 3 BHK and 4 BHK model apartments (9 AM – 7 PM daily)
- Site cleared and surveyed; boundary wall and approach-road work commencing
Launch — June 2026
- Telangana RERA registration number issued and active — RERA No. P02200010981
- Official launch on 25 May 2026 with confirmed pricing, inventory and Agreement to Sale templates
- EOI applicants convert to formal allotment with 10% milestone payment (less EOI)
- Bank-loan disbursement panel activated (HDFC, ICICI, SBI, Axis, Kotak, PNB, Bank of Baroda, LIC Housing)
Mobilisation — Q3 2026
- Site office and contractor camp set up
- Survey markings and gridding finalised against the master-plan layout
- Tree-preservation and landscape-survey work undertaken
- Soil-testing and geotechnical reports archived
Excavation & Piling — Q4 2026 to Q1 2027
- Two basement levels excavated for parking and utility rooms
- Pile foundations driven for all two iconic towers
- Retaining-wall structure for the basement walls cast
- Excavation milestone payment due from buyers (~10% of sale consideration)
Foundation — Q2 to Q3 2027
- Raft and pile-cap foundation cast for all two iconic towers
- Plinth-beam grid completed
- First-floor slab work begins
- Foundation milestone payment due (~10%)
Superstructure Rise — Q4 2027 through 2029
- Slab-by-slab vertical rise — approximately 1 slab every 3–4 weeks per tower
- By end-2028: 20+ slabs cast per tower (around 60% structural completion)
- By end-2029: Full structural rise to G + 45 floors
- Slab milestone payments billed at 1st, 10th, 20th and final slab stages
Finishing Works — 2030 to Q3 2031
- Brickwork and internal partitions across all apartments
- Plumbing and electrical rough-in
- Plastering, flooring, doors, windows, fittings
- Painting, false ceilings, kitchen modular install
- Lift commissioning, DG and HT power, sewage treatment plant
- Landscape and clubhouse fit-out completion
- Brickwork and flooring/fittings milestone payments due (~10% each)
Handover — June 2031
- Occupancy Certificate (OC) obtained from GHMC
- Snagging walkthroughs with buyers and punch-list corrections
- Final 5% milestone payment plus statutory charges (GST, stamp duty, registration)
- Apartment Owners' Association handover and key collection
How to Track Progress
- Site visits: Open to EOI applicants and confirmed buyers via the Kukatpally Experience Centre — 9 AM – 7 PM daily.
- Construction updates: Quarterly emailers sent to EOI applicants and booked buyers with photographs of build progress.
- Construction status dashboard: Watch this page — milestones are updated as they're certified by the project engineer.
- Telangana RERA portal: Post-registration, buyers can view quarterly progress reports on the TS-RERA portal under the project's registration number.
Frequently Asked Questions about Construction Status
1. What is the current status of Godrej Brooklyn Avenue?
The project is New Launch with bookings open. Telangana RERA (TS-RERA) registration is approved — RERA No. P02200010981 — ahead of the official launch on 25 May 2026.
2. When does on-site construction start?
Active site mobilisation begins in Q3 2026 immediately after the official launch. Excavation and piling for all two iconic towers run from Q4 2026 through Q1 2027.
3. When will the towers reach full height?
All two iconic towers are scheduled to reach their full 2 Basement + Stilt + 45 floor structural height by end of 2029. Finishing works run from 2030 through Q3 2031.
4. When is handover scheduled?
Handover and possession are targeted for June 2031, after the Occupancy Certificate is obtained from GHMC and snagging walkthroughs are complete.
5. Can I visit the site during construction?
Yes — EOI applicants and booked buyers can visit the Kukatpally Experience Centre at any time (9 AM – 7 PM daily). Once on-site construction begins, the centre will include a viewing deck over the active build zone.
6. How are construction-linked payments triggered?
Each milestone payment is triggered when the corresponding stage is certified complete by the project engineer. Buyers receive an invoice along with the engineer's certification document. The milestone schedule is detailed on the payment-plan page.